Redland Green School, Redland Court Road, Redland, Bristol BS7
The site uses multiple SuDS techniques including a green roof predominantly planted with sedum.
SuDS was selected to attenuate runoff as there is insufficient capacity in the local drainage system to take increased flows. There is an extensive green roof, predominantly planted with sedum.
A variety of methods were used: permeable surfaces; swales with weirs to control the rate of run-off; retention ponds with a storm-water overflow to a watercourse for additional flow. Infiltration techniques are used to minimise off-site runoff. Reason for choosing SuDS.
The extensive green roof system has a low maintenance sedum planting that provides cover and increased protection. The multi-use sports pitch are made of a permeable material. Drainage swales include treated timber baffle weirs to attenuate flows. Runoff from the car park is treated with a petrol interceptor before discharging into the swales. There are two dry retention ponds which are planted with a selection of species which thrive in saturated conditions, such as bistort. Stone filter drains further aid infiltration. The systems has an overflow to a nearby watercourse for extreme events.
In addition to managing runoff, benefits include provision of an outdoor classroom within the landscaping and an increase in biodiversity within the area. The roof also enhances the biodiversity of the area – previously a playing field with little other than amenity grass as cover.
The planning process was difficult as there was opposition to the siting of this new school. SuDS were required in this development as the local drainage network was unable to allow for additional flow from the site. The green roof is incorporated into the wider SuDS allowing for surface water to the retained on site.
It has been observed that flows have still discharged from the roof days after intense storms, demonstrating its attenuation role.
Part of routine grounds maintenance, grass cutting and checking the weirs for silt build-up. Low maintenance required since the roof has been installed includes routine weeding need throughout the year.
Design and construction - Building Design Partnership (BDP) London, Cowling Construction
Completed in September 2007